Lots of stuff going on inside...

A lot has happened in the last two weeks, electrical, piping and HVAC are in and drywall has begun and should finish in the next day or two. From there we're hoping for some brick and siding and initial flooring (hardwood). We're 60 days from closing and so far so good (fingers crossed).

Here's an updated picture of the front, with Foyer window and roof shingles installed.

Kitchen ceiling being installed along with completed piping, electrical and HVAC.

Sunroom ceiling installed


Foyer from top of steps